This project involved the construction of a 2 MW Solar Photovoltaic (PV) Array to serve as a supplementary renewable energy source for an industrial facility. The 8-acre site underwent precise clearing, grading, and drainage enhancements, including interior roadways to facilitate access. The scope encompassed grading adjustments totaling 3,200 cubic yards, importation and placement of 4,500 tons of road base for roadways, 365 cubic yards of concrete placement, and the installation of 375 posts to support 75 arrays, consisting of a total of 7500 PV modules.
JUDSON's First Solar Project
date
August 2023
location
Utah
client
Industrial Client
deliverables
- Heavy Civil Construction
- Structural Steel Erection
- Equipment Setting