Tailings unweighting for a Utah mining operation in Magna, UT. Our responsibilities included removing and repurposing excess materials left over from processing mined ore to ensure site safety and slope stabilization for future use.
Stabilization of Mining Slope for Future Use
date
location
client
Mining Site Reclamation
Tailings Unweighting for Mining in Utah
The purpose of this project was to remove 830,000 cubic yards of material off an unstable slope and place it on the impoundment to remove the potential issue of material sliding off the side of the slope. During the project, some changes were made to include the capping of specific areas of the impoundment and building a surcharge pad for a future pump station. The project also included the replacement of 2 HDPE lines (8″ and 10″) that ran through the project cut.